LandedCloud & Computing InfrastructureData Centre / Computing Facility2023SE-023

GDS Holdings / DayOne Data Centers · Malaysia

Global South·Southeast Asia·Group: GDS / DayOne

How to read these numbers: A purposive, publicly sourced case library, not a probability sample: counts describe the library, not market share. Monetary figures mix investment, revenue and user metrics — treat them as magnitude markers and defer to the verbatim description and source link.

What happened

GDS launched its Nusajaya Tech Park (NTP) data-centre campus in Iskandar Puteri, Johor in August 2023. Phase 1 comprises NTP1, NTP2 and NTP3 with 22,500 sqm (242,200 sq ft) of net floor area and 69.5 MW of IT power; GDS acquired the land in July 2021 and broke ground in April 2022 (roughly 16 months to delivery, ahead of the originally planned 2024 date). GDS CEO William Huang described the campus as a catalyst for the region's journey towards a world-class AI computing hub. GDS's international business was spun off as DayOne at the start of 2025. In June 2025 DayOne signed a 21-year contract for up to 500 MW of solar power with Tenaga Nasional Berhad under Malaysia's Corporate Renewable Energy Supply Scheme (CRESS), covering Nusajaya Tech Park and Kempas Tech Park, whose combined data-centre capacity is 120 MW.

Localisation & innovation

Overseas export of an intelligent Smart-DC construction-and-operations solution, achieving delivery in 14 months; a SIJORI cross-border hub model (Singapore connectivity + Johor land and energy + Batam expansion); a localized green-power-plus-energy-storage solution.

Structured fields

Host country
Malaysia
Region
Southeast Asia
AI segment
Cloud & Computing Infrastructure
Entry mode
Data Centre / Computing Facility
Entry year
2023
Deployment status
Landed
Capital direction
China->host (outbound deployment)
Company group
GDS / DayOne

Local partner

Nusajaya Tech Park

State-owned utilityState-linked partner

Scale

Phase 1 (NTP1-NTP3): 22,500 sqm net floor area and 69.5MW IT power (DatacenterDynamics, 11 Aug 2023). Nusajaya Tech Park and Kempas Tech Park have a combined data center capacity of 120MW (DatacenterDynamics, 12 Jun 2025). DayOne closed a RM15bn (approximately US$3.5bn) multi-currency financing (SolarQuarter, 16 Jun 2025). The previous 'Phase 2 50MW' phase-two figure is removed: it appears in no source I could locate.

Magnitude marker: ~3,500,000,000 USD

Monetary fields mix investment, revenue and user metrics. Treat them as magnitude markers only — never sum them across records; defer to the verbatim wording and source above.

Sources & notes

Record note: GDS is Shanghai-headquartered (NASDAQ: GDS / HKEX: 9698). Its international business was spun off and rebranded as DayOne at the start of 2025 after a Series B round; GDS retains a 35.6% non-controlling stake (DatacenterDynamics, 12 Aug 2025), so the 'Chinese-capital origin' framing is correct, but DayOne is no longer a GDS subsidiary and should not be described as one. The originally cited GDS press-release URL (gds-services.com/en/newsshow_82.html) is dead — it returns 'Information not found!' and the item is absent from the GDS press-release index at gds-services.com/en/news_19.html — hence the source swap to the DatacenterDynamics report of the same launch. in_esg_report='Yes' could not be independently verified.

Compiled from public reporting and company disclosures. Not legal or investment advice — cite the source link alongside any quotation.

Related records

Other records in the same host country or AI segment, ranked by source reliability and year.

ByteDance

Malaysia·Southeast Asia

LandedSE-022
Cloud & Computing InfrastructureData Centre / Computing Facility2022

ByteDance established its presence in Malaysia as the anchor tenant of the BDC MY06 hyperscale data center at Sedenak Tech Park in Johor (commissioned in 2022), and subsequently announced an investment of approximately RM10 billion (about US$2.1 billion) to establish an AI center in Malaysia, together with a further approximately RM1.5 billion to expand its data center. According to disclosures by the Johor Menteri Besar (Chief Minister), ByteDance's cumulative investment in AI data centers in Malaysia has exceeded RM29.5 billion, making it a core investor in Johor's AI computing cluster.

Cloud & Computing InfrastructureData Centre / Computing Facility2021

MY06 is the fourth hyperscale data-centre campus announced by Bridge Data Centres (per MIDA, 2021-12-02): approximately 40 acres, 100 MW of IT load, an investment of approximately RM2.5 billion over five years, three buildings, with Phase 1 in place by end-2022. It serves as the dedicated data centre anchored by ByteDance in Johor, Malaysia.

GDPR · PIPL · CCPA control mapping
Traceable AI · cited when sourced
ISO 27001 alignment in progress
WCAG 2.1 AA accessibility target
GDS Holdings / DayOne Data Centers in Malaysia — Cloud & Computing Infrastructure deployment record | HaiWen HQ