已落地云与算力基础设施数据中心 / 算力设施2021 年SE-021

秦淮数据(Bridge Data Centres)(Chindata Group / Bridge Data Centres) · 马来西亚(Malaysia)

全球南方·东南亚·集团:Chindata Group

数据口径:本库为目的性编制的公开案例集,非概率抽样;计数仅描述本库构成,不代表市场份额。金额字段混合投资额/营收/用户数等口径,仅作量级参考,请以原文描述与来源链接为准。

部署描述

来源原文(英文,未经改写)

MY06 is the fourth hyperscale data-centre campus announced by Bridge Data Centres (per MIDA, 2021-12-02): approximately 40 acres, 100 MW of IT load, an investment of approximately RM2.5 billion over five years, three buildings, with Phase 1 in place by end-2022. It serves as the dedicated data centre anchored by ByteDance in Johor, Malaysia.

本地化与创新要点

来源原文(英文,未经改写)

PPVC prefabricated modules manufactured in China and rapidly assembled on-site, delivering the hyperscale facility in 314 days — an example of efficiency-oriented/frugal innovation.

结构化字段

东道国
马来西亚(Malaysia)
区域
东南亚
AI 赛道
云与算力基础设施
进入方式
数据中心 / 算力设施
进入年份
2021
落地状态
已落地
资本流向
中国 → 东道国(对外部署)
企业集团
Chindata Group

本地伙伴

ByteDance

政府部门有国资 / 政府背景

规模

来源原文(英文,未经改写)

MY06 is planned to have 110MW of IT power capacity and cover an area of 38 acres (company-disclosed).

口径:企业披露

来源与备注

记录备注:RESOLVED: the MY06 code does not imply prior Malaysian sites specifically — MIDA (2021-12-02) states Bridge would operate '156+ MW of IT capacity across India and Malaysia', so the numbering spans a multi-country portfolio; no earlier named Malaysian site was verifiable. Keep the ownership caveat (Bain Capital control 2019–, privatisation 2023, Bridge DC operating HQ Singapore per MIDA). 2026-09-13 全库回扫复核(通过):回扫结论:PASS,deployment_status 保留 Landed、reliability 保留 High,均不降级。依据:原挂 4 条 URL 经复核员实测全属同一 PR 体系的企业来源——MIDA 2022/2021 为 MIDA+MDEC+BDC 联合通稿而 MIDA 已被本记录编为 local partner;W.Media 是 BDC 公关代理,13 段中 8 段与通稿 12 词窗口 100% 重合;bridgedatacentres.com 已 301 死链。复核员经 Wayback 补到两篇 DataCenterDynamics 具名报道(Dan Swinhoe 署名、无赞助标记、与通稿零逐字重合):2022-10-20 篇支撑设施已交付投运,2024-08-16 篇以现在时确认 ByteDance 为锚定租户,落地与高可靠因此成立。本次字段改动:补入该两条 DCD 存档来源,剔除死链 bridgedatacentres.com(裁定亦允许改标 dead)。档位未变故无恢复条件,但 PASS 以补挂 DCD 两条为前提,未补挂前不得视为已合规。裁定另列须执行项:拆 sources_total=5 / independent_sources=2、scale 拆为「已投运 19MW(MY06-1,2022-10 交付)/园区规划 110MW 三栋建设中」、partner_primary_type 停用 government 并重算派生字段、MIDA 的伙伴与官方来源两身份择一、description 末句改引 DCD 2024-08-16。

本页内容整理自公开报道与企业披露,不构成法律意见或投资建议;对外引用时请连同来源链接一并给出。

相关记录

同一东道国或同一 AI 赛道的其他记录(按来源可靠度与年份排序)。

云与算力基础设施数据中心 / 算力设施2023 年
来源原文(英文,未经改写)

GDS launched its Nusajaya Tech Park (NTP) data-centre campus in Iskandar Puteri, Johor in August 2023. Phase 1 comprises NTP1, NTP2 and NTP3 with 22,500 sqm (242,200 sq ft) of net floor area and 69.5 MW of IT power; GDS acquired the land in July 2021 and broke ground in April 2022 (roughly 16 months to delivery, ahead of the originally planned 2024 date). GDS CEO William Huang described the campus as a catalyst for the region's journey towards a world-class AI computing hub. GDS's international business was spun off as DayOne at the start of 2025. In June 2025 DayOne signed a 21-year contract for up to 500 MW of solar power with Tenaga Nasional Berhad under Malaysia's Corporate Renewable Energy Supply Scheme (CRESS), covering Nusajaya Tech Park and Kempas Tech Park, whose combined data-centre capacity is 120 MW.

云与算力基础设施数据中心 / 算力设施2022 年
来源原文(英文,未经改写)

ByteDance established its presence in Malaysia as the anchor tenant of the BDC MY06 hyperscale data center at Sedenak Tech Park in Johor (commissioned in 2022), and subsequently announced an investment of approximately RM10 billion (about US$2.1 billion) to establish an AI center in Malaysia, together with a further approximately RM1.5 billion to expand its data center. According to disclosures by the Johor Menteri Besar (Chief Minister), ByteDance's cumulative investment in AI data centers in Malaysia has exceeded RM29.5 billion, making it a core investor in Johor's AI computing cluster.